Page 5 - Al-Rashed Newsletter January 2020
P. 5

SHIPPING WORLD
                                             AL-RASHED PROJECTS- MUTLA SUB


                                                                      STATION




                                             Al-Rashed International Shipping Co Projects & Logistics Division in contract with M/s
                                             Sayed Hamid Behbehani & Sons Co. W.L.L. (SHBC) Heavy Lift divisions handled new
                                             sub-station projects for PAHW Mutla Project secured by Al-Ahleia Switchgear Co. who
                                             executes  turnkey-EPC  projects  for  construction  of  400kV/132kV/11kV  Primary
                                             Substations for PAHW, MEW Kuwait.
                                             These  Substations  incorporate  equipment  such  as  300MVA/30MVA  Power
                                             Transformers,  1000KVA/250KVA  Station  Transformers,  Neutral  Grounding  Resistors,
                                             400kV/132KV Gas Insulated Switchgears, 11kV Double Busbar Switchgear, associated
                                             Control & Relay Panels and Battery & Battery chargers and shunt reactors.
                                             Al-Rashed’s scope of work included receiving and delivery of Shunt Reactors and all
                                             general accessories from Shuaiba port and delivery to the Mutla Sub Station sites (1Z,
                                             2Z  and  3Z)  as  well  as  the  Jacking  &  Skidding  Operations  of  300MVA  transformers
                                             which  includes  placing  &  aligning  the  transformers  on  foundation  as  per  client’s
                                             requirement  and  specifications.  The  shipments  arrived  on  3  different  vessels  from
                                             November  2019  to  January  2020,  where  Al-Rashed  was  also  the  appointed  vessel
                                             agent for all 3 voyages.

                                             JACKING STEPS
                                             The  first  step  in  the  jacking  and  cribbing  procedure  is  to  set  up  a  safe  jacking
                                             arrangement.  This  arrangement  consists  of  two  cribbing  piles  and  two  identical,
                                             hydraulically interconnected (hydraulically interconnected jacks are jacks that share a
                                             common hydraulic supply line from a single hydraulic manifold and pumping unit in a
                                             configuration so that the lifting pressure in both jacks is always equal) jacks placed at
                                             one end of the piece of transformer at the manufacturer-approved equipment support
                                             points.
                                             The cribbing piles at the jacking end provide safety in the event that the hydraulic jacks
                                             fail to support the load. These piles will also support the load when the jacks are not
                                             used  or  removed.  The  other  end  of  the  equipment  rests  hard  on  cribbing  to  provide
                                             stability. This is very important because it prevents the load from rolling during jacking.
                                             This arrangement provides predictable loads in the jacks and at the cribbing points and
                                             prevents two-pointing. During the jacking operation, the cribbing piles adjacent to the
                                             jacks should be continuously shimmed to minimize the distance that the load will settle
                                             in the event that a jack fails.
                                             The  next  step  is  to  extend  the  two  interconnected  jacks  high  enough  to  install  the
                                             cribbing layer. The jacks will extend equally because the opposite end is resting hard
                                             against its cribbing. Install the layer of cribbing under the jacked end. Shim the cribbing
                                             tight with steel shims or hardwood. Next, slowly release the pressure in both jacks using
                                             a common needle type valve.

                                             SKIDDING STEPS
                                             Moving  a  transformer  by  skidding  requires  services  and  equipment  which  can  be
                                             supplied only by an experienced heavy-equipment moving contractor.
                                             If  lifting  by  crane  is  impractical,  the  transformer  can  be  moved  along  the  ground  by
                                             Skidding  on  greased  rail  beam  Moving  transformer  along  the  railway  involves  four
                                             distinct steps:
                                             a)  Building  the  railway;  Setting  Supporting  Beams,  Wooden  Block,  and  Rail,  setting
                                             between Foundation and Multi Axle
                                             b) Moving the Transformer from the multi axle to the railway;
                                             c) Skidding along the railway;
                                             d) Positioning the transformer on designated place.
   1   2   3   4   5   6   7   8   9   10